Progress photo 39

Progress Photo Collection

18th March 2020
Overview of the site
Balancing tank foundation work in progress
Jogging track road base work in progress.
Landscaping work in progress.
20th February 2020
Overview for Elemen P2
Installation of the passenger glass lift in progress.
Installation of the staircase louver completed.
80% completion for the internal building painting work.
29th January 2020
Overview Tower A from fitness amenities floor.
Podium area.
Swimming pool in progress.
Swimming pool in progress.
Over view of Presint 2
Over view of Presint 2
Over view of Presint 2
Elemen Presint 2 rooftop view
Elemen Presint 2 rooftop view
Elemen Presint 2 rooftop view
Elemen Presint 2 rooftop view
Elemen Presint 2 rooftop view
Elemen Presint 2 rooftop view
16th December 2019
Overview
Fitness amenities area
Overall view of the podium
Basketball court flooring work in progress
Swimming pool tiling work in progress
6th November 2019
Overview.
Sewerage treatment plant (STP) work in progress.
Carpark painting work in progress.
Podium work in progress.
5th October 2019
Overview.
Sewer pipe work in progress.
Construction sewerage treatment plant (STP) in progress.
Landscaping in progress.
6th September 2019
Overview.
Carpark floor screeding work in progress
External drainage work in progress
2nd August 2019
Overview.
Swimming pool water piping work.
Painting on podium 3rd & 4th floor.
External drainage work.
20th June 2019
Brickwork @ staircase in progress
Lift lobby tiling work
Overview of the site
9th April 2019
Commercial shop lot external wall plastering work in progress