Progress photo 39

Progress Photo Collection

6th September 2019
Overview.
Carpark floor screeding work in progress
External drainage work in progress
2nd August 2019
Overview.
Swimming pool water piping work.
Painting on podium 3rd & 4th floor.
External drainage work.
20th June 2019
Brickwork @ staircase in progress
Lift lobby tiling work
Overview of the site
9th April 2019
Commercial shop lot external wall plastering work in progress