Progress photo 65

6th September 2018 - Amneties floor slab (future gym + swimming pool)
1st August 2018 - 20th floor slab rebar & formwork in progress
2nd July 2018 - 17th floor slab rebar & formwork in progress.
1st June 2018 - 14th floor slab rebar & formwork in progress.
7th May 2018 - 12th floor slab rebar & formwork in progress.
2nd April 2018 - 10th floor slab casted
1st March 2018 - Commercial shop ground beam's rebar & formwork in progress.
1st February 2018 - 7th floor slab rebar & formwork in progress.
5 January 2018 - 6th floor slab casted
1 December 2017 - Commercial shop ground floor slab casted
1 November 2017 - 2nd Floor slab rebar & formwork in progress
1 October 2017 - Ground & 2nd floor slab rebar & formwork in progress
1 September 2017 Photo 1 & 2: Ground floor slab concrete casting work in progress. Photo 3: 1st floor slab casted (partial).
1 August 2017 - Ground beam, slab & column work in progress
1 July 2017 - Ground beam, ground slab & ground column in progress.
1 June 2017 - Ground beam, ground slab & retaining wall in progress.
16 May 2017 - Ground beam, ground slab & earth back-filling works in progress.
20 April 2017 - Ground beam concrete casting & rebar works in progress.
27 March 2017 - Overall site view
27 March 2017 - Steel bar fabrication in progress
27 March 2017 - Concrete mixing in progress
27 March 2017 - Contractor site office
25 November 2016 - Column stump casted
11 May 2016 - Pile Cap Casting in progress
17 April 2016 - Site Preparation
18 March 2016 - Site Preparation